Envision AESC South Carolina Plant (Expansion #2)
Envision AESC
Florence, SC, USA
34.2033442, -79.7318501
The Big Green Machine Site ID: 98C
Additional Information:
Sector: Batteries
Activity: Manufacturing
Product: Battery Cell
Project Announcement Date: 3/26/2024
Target for Starting Production: 2027
Announced Post Inflation Reduction Act: Yes
Current Annual Production: ? GWh
Project Status: Planned
Target Jobs: 1080
Current Jobs: ?
Capital Investment: $1500 million
Congressional District: SC7
Government Subsidies:
Local/State: $111 million
Tracked Expansions and/or Acquisitions:
This site has 2 major expansion(s).
Those expansion(s) are tracked below:
Site 98A: Envision AESC South Carolina Plant
Site 98B: Envision AESC South Carolina Plant (Expansion #1)