INDIVIDUAL FACILITIES AND SELECTED SOURCES

Below is basic information about individual facilities in our database and selected sources we've drawn on to support the analysis.  To navigate to other sites, use the search page.

Company logo

PlusCAM Plant

6K

Jackson, TN, USA

35.5966781, -88.9444183

The Big Green Machine Site ID: 75

Additional Information:

Sector: Batteries

Activity: Materials Processing

Product: Battery Cell Components


Project Announcement Date: 10/19/2022

Target for Starting Production: 2024

Announced Post Inflation Reduction Act: No


Target Annual Production: 13000 tpa

Current Annual Production: ? tpa

Project Status: Under Construction


Target Jobs: 230

Current Jobs: ?

Capital Investment: $216 million

Congressional District: TN8

Government Subsidies:

Federal

Bipartisan Infrastructure Funding: $50 million

bottom of page