First Solar Jim Nolan Center

First Solar

Lake Township, OH, USA

41.556563, -83.5401148

The Big Green Machine Site ID: 624

Additional Information:

Sector: Solar

Activity: Manufacturing

Product: Solar Modules


Project Announcement Date: 6/9/2021

Target for Starting Production: 2024

Date Commercial Production Started: 7/18/2024

Announced Post Inflation Reduction Act: No


Target Annual Production: 3 GW

Project Status: Pilot


Target Jobs: 650

Current Jobs: 650

Capital Investment: $500 million

Congressional District: OH9

Government Subsidies:

We currently have no government subsidies tracked for this site.