Company logo

Electrovaya US Gigafactory

Electrovaya

Jamestown, NY, USA

-79.1952214, 42.1083442

The Big Green Machine Site ID: 60

Additional Information:

Sector: Batteries

Activity: Manufacturing

Product: Battery Cell


Project Announcement Date: 10/1/2022

Target for Starting Production: 2025

Date Commercial Production Started:

Announced Post Inflation Reduction Act: Yes


Target Annual Production: 0.3 GWh

Operating Status: Under Construction


Target Jobs: 250

Capital Investment: $40 million

Congressional District: NY23

Government Subsidies:

Local/State: $6.5 million

Selected Sources:

“Electrovaya to Establish Lithium-Ion Gigafactory in New York State”, Electrovaya, 02 Oct 2022. 🔗


“Electrovaya Seeking Investment For Ellicott Factory”, John Whittaker, post-journal.com, 17 Feb 2023. 🔗



“Electrovaya Provides Update on Planned New York Gigafactory”, Yahoo Finance, 02 Aug 2023. 🔗


“Electrovaya Has Big Plans For Ellicott Battery Factory If Construction Funding Is Secured”, John Whittaker, post-journal.com, 05 Jan 2024. 🔗


“Annual Battery Technology & Investor Day”, electrovaya.com, 11 Jun 2024. 🔗


“Ellicott Factory Financing Package Nears Completion”, John Whittaker, post-journal.com, 16 Aug 2024. 🔗


“Ellicott Factory Financing Package Nears Completion”, John Whittaker, post-journal.com, 16 Aug 2024. 🔗


“Electrovaya buying, hiring, for N.Y. battery factory”, Chad Elmore, Power Progress, 15 Jan 2025. 🔗


“Electrovaya Pushes Up Ellicott Plant Opening”, John Whittaker, post-journal.com, 14 Feb 2025. 🔗


“Electrovaya receives $51-million EXIM loan to expand battery manufacturing in the US”, Jonathan Spira, Charged Electric Vehicle, 31 Mar 2025. 🔗


Tracked Expansions, Acquisitions, or Related Sites:

We currently have no related projects tracked for this site.

This website, dashboard, and dataset are maintained by Jay Turner and student researchers in the Environmental Studies Department at Wellesley College. It is updated at least monthly. The data presented are compiled from publicly available sources. Summary statistics are incomplete and omit data from sites where publicly available information (regarding capital investments, employment levels, etc.) is unavailable. While we make every effort to ensure the information presented here is accurate, the information should be treated as estimates. We assume no responsibility or liability for any errors or omissions. The information contained in this site is provided on an "as is" basis with no guarantees of completeness, accuracy, or usefulness. The Big Green Machine® is a registered trademark. Please submit feedback using this formData on this site last updated on April 19, 2025. 

Wellesley College Logo
bottom of page