INDIVIDUAL FACILITIES AND SELECTED SOURCES
Below is basic information about individual facilities in our database and selected sources we've drawn on to support the analysis. To navigate to other sites, use the search page.
QCell Cartersville Factory
Qcells
Cartersville, GA, USA
34.1200497957216, -84.7429886039167
The Big Green Machine Site ID: 371
Additional Information:
Sector: Solar
Activity: Manufacturing
Product: Cells
Project Announcement Date: 1/11/2023
Target for Starting Production: 2024
Date Commercial Production Started: 4/4/2024
Announced Post Inflation Reduction Act: Yes
Target Annual Production: 3.3 GW
Project Status: Operating
Target Jobs: 1950
Capital Investment: $2500 million
Congressional District: GA11
Government Subsidies:
We currently have no government subsidies tracked for this site.
Tracked Expansions and/or Acquisitions:
We currently have no related projects tracked for this site.