CS Wind America Tower Pueblo Facility (expansion)

CS Wind

Pueblo, CO, USA

-104.6215755, 38.1733607

The Big Green Machine Site ID: 338C

Project Timeline

Project Timeline Unavailable (Insufficient Information)

Additional Information:

Sector: Wind

Activity: Manufacturing

Product: Tower


Project Announcement Date: 4/1/2023

Target for Starting Production: 2028

Date Commercial Production Started:

Announced Post Inflation Reduction Act: Yes


Target Annual Production: 10000 Tower Sections

Current Annual Production: 5000 Tower Sections

Operating Status: Under Construction


Target Jobs: 1500

Current Jobs: 650

Capital Investment: $250 million

Congressional District: CO3

Government Subsidies:

We currently have no government subsidies tracked for this site.

Selected Sources:

“President Biden set to visit CS Wind plant in Pueblo”, governorswindenergycoalition.org, 28 Nov 2023. 🔗


“Pueblo plant expansion driven by Inflation Reduction Act”, KOAA News 5, 15 Oct 2023. 🔗


“CS Wind to acquire Vestas’ Pueblo tower factory to strengthen local job creation and wind energy supply chain”, Vestas, 02 Jun 2021. 🔗


“CS Wind Breaks Ground on Expansion at World’s Largest Wind Turbine Tower Manufacturing Plant, Plans to Create 850 New Jobs in Pueblo, Colorado”, burnsmcd.com, 03 Apr 2023. 🔗


“The 9 largest commercial construction starts of April 2025”, Sebastian Obando, Construction Dive, 21 Apr 2025. 🔗


Tracked Expansions, Acquisitions, or Related Sites:

I'm a paragraph. Click here to add your own text and edit me. It's easy.

This website, dashboard, and dataset are maintained by Jay Turner and student researchers in the Environmental Studies Department at Wellesley College. It is updated at least monthly. The data presented are compiled from publicly available sources. Summary statistics are incomplete and omit data from sites where publicly available information (regarding capital investments, employment levels, etc.) is unavailable. While we make every effort to ensure the information presented here is accurate, the information should be treated as estimates. We assume no responsibility or liability for any errors or omissions. The information contained in this site is provided on an "as is" basis with no guarantees of completeness, accuracy, or usefulness. The Big Green Machine® is a registered trademark. The Big Green Machine Data © 2024 by Jay Turner is licensed under CC BY 4.0.  Please submit feedback using this formData on this site last updated on January 20, 2026. 

Wellesley College Logo
bottom of page