top of page

INDIVIDUAL FACILITIES AND SELECTED SOURCES
Below is basic information about individual facilities in our database and selected sources we've drawn on to support the analysis.  To navigate to other sites, use the search page.

Company logo

Kreisel Electric Products

Deere & Company

Kernersville, NC, USA

-80.0929018140424, 36.137044675814

The Big Green Machine Site ID: 294

Additional Information:

Sector: Batteries

Activity: Manufacturing

Product: Battery Pack


Project Announcement Date: 8/15/2023

Target for Starting Production: 2024

Announced Post Inflation Reduction Act: Yes


Target Annual Production: 2 GWh

Operating Status: Planned


Capital Investment: $69.6 million

Congressional District: Republican

Government Subsidies:

Local/State: $0.1 million

Selected Sources:

“Deere Picks New U.S. Battery Hub”, David Mantey, Manufacturing.net, 16 Aug 2023. 🔗


“Deere & Company-Kreisel Electric GMBH Plan Kernersville, North Carolina, Operations”, Area Development News Desk, Area Development, 16 Aug 2023. 🔗


Tracked Expansions, Acquisitions, or Related Sites:

We currently have no related projects tracked for this site.

This website, dashboard, and dataset are maintained by Jay Turner and student researchers in the Environmental Studies Department at Wellesley College. It is updated at least monthly. The data presented are compiled from publicly available sources. Summary statistics are incomplete and omit data from sites where publicly available information (regarding capital investments, employment levels, etc.) is unavailable. While we make every effort to ensure the information presented here is accurate, the information should be treated as estimates. We assume no responsibility or liability for any errors or omissions. The information contained in this site is provided on an "as is" basis with no guarantees of completeness, accuracy, or usefulness. 