INDIVIDUAL FACILITIES AND SELECTED SOURCES
Below is basic information about individual facilities in our database and selected sources we've drawn on to support the analysis. To navigate to other sites, use the search page.
Tesla Kato Road Facility
Tesla
Fremont, CA, USA
-121.9276199, 37.4692662
The Big Green Machine Site ID: 166
Additional Information:
Sector: Batteries
Activity: Manufacturing
Product: Battery Cell
Project Announcement Date: 6/1/2020
Target for Starting Production: 2021
Date Commercial Production Started: 9-22-2020
Announced Post Inflation Reduction Act: No
Target Annual Production: 10 GWh
Current Annual Production: 4.5 GWh
Operating Status: Pilot
Congressional District: Democrat
Government Subsidies:
We currently have no government subsidies tracked for this site.
Selected Sources:
#1: Insideevs - insideevs.com
#2: Tesla confirms 4680 battery cell production is now enough for 1,000 cars a week - electrek.co
Tracked Expansions and/or Acquisitions:
We currently have no related projects tracked for this site.